Kenya DC Tracker · Subsea cables

The cables under Mombasa, tracked.

Every international system at Kenya's coast: what is live, what is landed but not yet counted, and what is only announced. The same discipline as the capacity pipeline, a cable joins the live count when it carries traffic, not when it makes headlines.

7

Live systems · in service at Mombasa

1

Landed, RFS pending · not counted as live

2

Announced / planned · incl. first coastal route

Sep 2026

Dataset verified · monthly sweep

The full slate

Sorted by status, then by ready-for-service date. Design capacity is the operator-reported figure and is usually far above lit capacity, which is not published and is deliberately not estimated here.

In serviceCarrying traffic on the Kenya segment

  • TEAMSThe East African Marine System2009

    Mombasa  ·  Telkom Kenya on behalf of the Government of Kenya  ·  1.28 Tbps at launch, subsequently upgraded

    Kenya's first submarine cable. Cut international bandwidth costs by over 90% and connected Kenya to the UAE and onwards to Europe and Asia.

    High confidence · verified 2026-09full explainer

  • SEACOM2009

    Mombasa  ·  Privately owned (SEACOM)

    Connects South Africa, Mozambique, Tanzania and Kenya to Europe and India. Played a crucial role in breaking East Africa's bandwidth monopoly.

    High confidence · verified 2026-09full explainer

  • EASSyEastern Africa Submarine System2010

    Mombasa (branch)  ·  21-member consortium  ·  Upgraded to 48 Tbps (reported)

    Runs from South Africa to Sudan with a Mombasa branch, connecting to Europe via multiple landing points.

    High confidence · verified 2026-09full explainer

  • LION2Lower Indian Ocean Network 22012

    Mombasa  ·  Orange-led consortium

    Links Mombasa to Madagascar and Réunion; ready for service since April 2012.

    High confidence · verified 2026-09full explainer

  • DARE1Djibouti Africa Regional Express2021

    Mombasa  ·  Djibouti Telecom-led consortium

    In service since February 2021, connecting Djibouti, Mogadishu and Mombasa; designed to add diversity for landlocked East African nations.

    High confidence · verified 2026-09full explainer

  • PEACEPakistan and East Africa Connecting Europe2022

    Mombasa (branch)  ·  Huawei Marine Networks-built, PEACE consortium

    Provides a new route to Europe via Pakistan and the Middle East, with a branch landing in Mombasa.

    Medium confidence · verified 2026-09full explainer

  • 2Africa2024

    Mombasa · Mtwapa  ·  Meta-led consortium  ·  180 Tbps design capacity

    One of the largest subsea projects globally. Its Kenya segment went live in June 2024; the core system was completed in November 2025.

    High confidence · verified 2026-09full explainer

Landed, RFS pendingAshore, but no ready-for-service date announced

  • Africa-1no RFS date

    Mombasa  ·  Telecom Egypt-led consortium

    The cable has come ashore at Mombasa but its ready-for-service date has not been announced, so DC254 does not count it among the live systems yet.

    Medium confidence · verified 2026-09full explainer

AnnouncedFormally announced build, host or consortium named

  • Darajano RFS date

    Mombasa (planned)  ·  Meta-backed, hosted by Safaricom

    Announced October 2025 to run from Salalah in Oman to Mombasa with 24 fibre pairs. In development; does not change the live count.

    Medium confidence · verified 2026-09full explainer

PlannedAnnounced intent, pre-contract or pre-construction

  • LuLuLuLu coastal cable systemno RFS date

    Mombasa to Lamu coastal corridor: Vipingo SEZ, Kilifi, Malindi  ·  INDOI Ltd (IOX) and Blue Trade Investments consortium  ·  Up to 60 Tbps per fibre pair, 144 pairs (announced)

    Announced at ITW Africa 2026 (September 2026): a ~500 km coastal diversity route pairing a subsea span with a protected terrestrial path. Readiness-for-service target Q2 2028, subject to contract execution; no supplier named and construction not started at announcement.

    Medium confidence · verified 2026-09full explainer

The counting rule

The live count changes on ready-for-service, not on landing. Africa-1 is ashore but not counted until an RFS date is published; Daraja and LuLu are tracked so the pipeline is visible, never counted. Where a claim and the evidence part ways, the row says so. Sources per row; full methodology on the linked explainers.